Portfolio

Completed

Flying Bark Studio

The whole building, from the street substation to the production floor.

Flying Bark Studio
Flying Bark Studio · AlexandriaCable tray and services
Location
Alexandria, Sydney
Sector
Production studio
Role
Electrical construction, whole building
Status
Completed

Overview

An animation studio is a building that cannot go dark. Every desk is a workstation, the render and server rooms run through the night, and a supply fault stops the whole pipeline. ATAS delivered the electrical for the entire building as one contract, from the kerb to the last outlet.

The work began in the street: trenching and conduits for the new supply, a chamber substation behind louvred doors, consumer mains to a new main switchboard, then submains on cable ladder to distribution boards on every floor. Above the ceilings, power and data run in segregated basket tray through the exposed concrete frame, sweeping around columns and dropping to workstation clusters, edit suites, meeting rooms and the server room. Linear LED lighting runs through the open floors, feature lighting through the shared spaces, with emergency and exit lighting throughout. Tested, certified and handed over with as-builts.

DeliverablesCertificate of Compliance, test results, switchboard schedules and as-builts

Flying Bark Studio, detail

Electrical scope

  • Level 2 connection: trenching, conduits and consumer mains from the street
  • Chamber substation and transformer installation
  • Main switchboard, metering and submains on cable ladder
  • Distribution boards to every floor
  • Segregated power and data in basket tray through exposed services
  • Workstation power and structured cabling across the production floors
  • Server room and edit suite power on dedicated circuits
  • Linear LED lighting through exposed ceilings, feature lighting in shared spaces
  • Meeting room AV, kitchen and breakout services
  • Emergency and exit lighting throughout
  • Testing, certification and as-builts